New York, NY solar permits

Residential solar permits in New York, NY were issued in a median of 6 business days in 2024, with a median permit cost of $982.

6 business daysto permit, median (2024)
13 business daysto inspection
1 business dayfinal interconnection to PTO
$982median permit cost

Permitting and interconnection in New York

Permit issued (median)6 business days (2024)
Inspection scheduled (median)13 business days (2024)
Utility approval before install (median)Same day (2023)
Final interconnection to PTO (median)1 business day (2024)
Median residential permit cost$982
Online submissionOnline portal or email
Instant permittingNot available
Same-day, over-the-counter permitsNot available
Structural review, systems under 10 kWRequired
Electrical review, systems under 10 kWNot required
Inspections required2
Rough-in inspectionRequired
SolSmart designationGold · 3-day permit commitment

A New York plan set from Ballast

Enter the address and Ballast finds the jurisdiction and the utility, pulls the aerial and parcel line, and builds the set on ANSI B: cover, site plan, roof or array plan, attachment details, line diagrams, NEC calculations, labels and spec sheets.

  • Checks run under the code edition New York has adopted, each with the article cited.
  • Any correction New York sends back becomes a rule for the jurisdiction, so the next set already answers it.
  • The Solar Agent follows the permit through to approval, then moves the job on to interconnection and install.

Questions

How long does a solar permit take in New York, NY?

The median time to issue a residential solar permit in New York was 6 business days in 2024, according to NREL SolarTRACE.

How much does a solar permit cost in New York?

The median residential solar permit cost in New York is $982 (NREL SolarTRACE). Confirm the current fee schedule with the jurisdiction.

How many inspections does a solar install need in New York?

New York requires 2 inspections for a residential solar installation, including a rough-in inspection.

Source: SolarTRACE, National Renewable Energy Laboratory (NREL), 2025-09-09 release. Times are medians for residential solar in the year shown. Requirements change — confirm current rules, fees and forms with the jurisdiction before you submit.