Home › Permits › California › Los Angeles County

Los Angeles County, CA solar permits

Residential solar permits in Los Angeles County, CA were issued in a median of 12 business days in 2018, with a median permit cost of $378.

12 business daysto permit, median (2018)
53 business daysto inspection
3 business daysfinal interconnection to PTO
$378median permit cost

Permitting and interconnection in Los Angeles County

Permit issued (median)12 business days (2018)
Inspection scheduled (median)53 business days (2018)
Utility approval before install (median)7 business days (2023)
Final interconnection to PTO (median)3 business days (2023)
Median residential permit cost$378
Online submissionInstant online permitting
Instant permittingYes (Other)
Same-day, over-the-counter permitsNot available
Structural review, systems under 10 kWRequired
Electrical review, systems under 10 kWOnly in some cases
Inspections required1
Rough-in inspectionRequired
Third-party plan reviewNo

A Los Angeles County plan set from Ballast

Enter the address and Ballast finds the jurisdiction and the utility, pulls the aerial and parcel line, and builds the set on ANSI B: cover, site plan, roof or array plan, attachment details, line diagrams, NEC calculations, labels and spec sheets.

  • Checks run under the code edition Los Angeles County has adopted, each with the article cited.
  • Any correction Los Angeles County sends back becomes a rule for the jurisdiction, so the next set already answers it.
  • The Solar Agent follows the permit through to approval, then moves the job on to interconnection and install.

Questions

How long does a solar permit take in Los Angeles County, CA?

The median time to issue a residential solar permit in Los Angeles County was 12 business days in 2018, according to NREL SolarTRACE.

How much does a solar permit cost in Los Angeles County?

The median residential solar permit cost in Los Angeles County is $378 (NREL SolarTRACE). Confirm the current fee schedule with the jurisdiction.

How many inspections does a solar install need in Los Angeles County?

Los Angeles County requires 1 inspection for a residential solar installation, including a rough-in inspection.

Source: SolarTRACE, National Renewable Energy Laboratory (NREL), 2025-09-09 release. Times are medians for residential solar in the year shown. Requirements change — confirm current rules, fees and forms with the jurisdiction before you submit.