Home › Permits › California › Fontana

Fontana, CA solar permits

Residential solar permits in Fontana, CA were issued in a median of 12 business days in 2019, with a median permit cost of $338. Instant permitting through SolarAPP+ is available.

12 business daysto permit, median (2019)
13 business daysto inspection
18 business daysfinal interconnection to PTO
$338median permit cost

Permitting and interconnection in Fontana

Permit issued (median)12 business days (2019)
Inspection scheduled (median)13 business days (2019)
Utility approval before install (median)1 business day (2019)
Final interconnection to PTO (median)18 business days (2019)
Median residential permit cost$338
Online submissionInstant online permitting
Instant permittingYes (SolarAPP+)
Same-day, over-the-counter permitsNot available
Structural review, systems under 10 kWRequired
Electrical review, systems under 10 kWNot required
Inspections required1
Rough-in inspectionNot required
Third-party plan reviewYes

SolarAPP+ in Fontana

Fontana issues residential solar permits instantly through SolarAPP+. Covered: PV, PV + storage, Main panel upgrade. Not covered: Main breaker derate — those go through standard plan review. The city's SolarAPP+ page.

Ballast lays out the SolarAPP+ application data in the order the form asks, so the submission is a copy-through rather than a re-type. How SolarAPP+ works.

A Fontana plan set from Ballast

Enter the address and Ballast finds the jurisdiction and the utility, pulls the aerial and parcel line, and builds the set on ANSI B: cover, site plan, roof or array plan, attachment details, line diagrams, NEC calculations, labels and spec sheets.

  • Checks run under the code edition Fontana has adopted, each with the article cited.
  • Any correction Fontana sends back becomes a rule for the jurisdiction, so the next set already answers it.
  • The Solar Agent follows the permit through to approval, then moves the job on to interconnection and install.

Questions

How long does a solar permit take in Fontana, CA?

The median time to issue a residential solar permit in Fontana was 12 business days in 2019, according to NREL SolarTRACE.

How much does a solar permit cost in Fontana?

The median residential solar permit cost in Fontana is $338 (NREL SolarTRACE). Confirm the current fee schedule with the jurisdiction.

How many inspections does a solar install need in Fontana?

Fontana requires 1 inspection for a residential solar installation.