Home › Permits › California › Desert Hot Springs

Desert Hot Springs, CA solar permits

Residential solar permits in Desert Hot Springs, CA were issued in a median of 6.5 business days in 2019, with a median permit cost of $474. Instant permitting through SolarAPP+ is available.

6.5 business daysto permit, median (2019)
14 business daysto inspection
3 business daysfinal interconnection to PTO
$474median permit cost

Permitting and interconnection in Desert Hot Springs

Permit issued (median)6.5 business days (2019)
Inspection scheduled (median)14 business days (2019)
Utility approval before install (median)1 business day (2019)
Final interconnection to PTO (median)3 business days (2018)
Median residential permit cost$474
Online submissionInstant online permitting
Instant permittingYes (SolarAPP+)
Same-day, over-the-counter permitsNot available
Structural review, systems under 10 kWRequired
Electrical review, systems under 10 kWNot required
Inspections required2
Rough-in inspectionNot required
Third-party plan reviewNo

SolarAPP+ in Desert Hot Springs

Desert Hot Springs issues residential solar permits instantly through SolarAPP+. Covered: PV, PV + storage, Main panel upgrade, Main breaker derate. The city's SolarAPP+ page.

Ballast lays out the SolarAPP+ application data in the order the form asks, so the submission is a copy-through rather than a re-type. How SolarAPP+ works.

A Desert Hot Springs plan set from Ballast

Enter the address and Ballast finds the jurisdiction and the utility, pulls the aerial and parcel line, and builds the set on ANSI B: cover, site plan, roof or array plan, attachment details, line diagrams, NEC calculations, labels and spec sheets.

  • Checks run under the code edition Desert Hot Springs has adopted, each with the article cited.
  • Any correction Desert Hot Springs sends back becomes a rule for the jurisdiction, so the next set already answers it.
  • The Solar Agent follows the permit through to approval, then moves the job on to interconnection and install.

Questions

How long does a solar permit take in Desert Hot Springs, CA?

The median time to issue a residential solar permit in Desert Hot Springs was 6.5 business days in 2019, according to NREL SolarTRACE.

How much does a solar permit cost in Desert Hot Springs?

The median residential solar permit cost in Desert Hot Springs is $474 (NREL SolarTRACE). Confirm the current fee schedule with the jurisdiction.

How many inspections does a solar install need in Desert Hot Springs?

Desert Hot Springs requires 2 inspections for a residential solar installation.

Source: SolarTRACE, National Renewable Energy Laboratory (NREL), 2025-09-09 release. Times are medians for residential solar in the year shown. Requirements change — confirm current rules, fees and forms with the jurisdiction before you submit.