Home › Permits › Arizona

Arizona solar permits

Permit timelines, fees, reviews and inspections for 24 Arizona jurisdictions. Across them, the median time to a residential solar permit is 8 business days.

Arizona utility interconnection

UtilityApproval before installApply viaFeeUtility responseSystem size capCapacity map
Arizona Public Service Co (APS)RequiredPortalNo fee5 days (required by rule)No size cap on recordNot on record
Salt River Project (SRP)RequiredPortalNo fee5 days (required by rule)No size cap on recordNot on record
Tucson Electric Power Co (TEP)RequiredPortalNo fee5 days (required by rule)125% of annual usageHosting capacity map

All utilities

Source: SolarTRACE, National Renewable Energy Laboratory (NREL), 2025-09-09 release. Times are medians for residential solar in the year shown. Requirements change — confirm current rules, fees and forms with the jurisdiction before you submit.