0.5 business daysto permit, median (2023)
12.5 business daysto inspection
1.5 business daysfinal interconnection to PTO
Plan reviewhow permits are issued
Permitting and interconnection in Greeley
| Permit issued (median) | 0.5 business days (2023) |
|---|---|
| Inspection scheduled (median) | 12.5 business days (2023) |
| Utility approval before install (median) | 11 business days (2022) |
| Final interconnection to PTO (median) | 1.5 business days (2023) |
| Online submission | Online portal or email |
| Instant permitting | Not available |
| Same-day, over-the-counter permits | Available |
| Structural review, systems under 10 kW | Required |
| Electrical review, systems under 10 kW | Required |
| Inspections required | 1 |
| Rough-in inspection | Not required |
A Greeley plan set from Ballast
Enter the address and Ballast finds the jurisdiction and the utility, pulls the aerial and parcel line, and builds the set on ANSI B: cover, site plan, roof or array plan, attachment details, line diagrams, NEC calculations, labels and spec sheets.
- Checks run under the code edition Greeley has adopted, each with the article cited.
- Any correction Greeley sends back becomes a rule for the jurisdiction, so the next set already answers it.
- The Solar Agent follows the permit through to approval, then moves the job on to interconnection and install.
Questions
How long does a solar permit take in Greeley, CO?
The median time to issue a residential solar permit in Greeley was 0.5 business days in 2023, according to NREL SolarTRACE.
How many inspections does a solar install need in Greeley?
Greeley requires 1 inspection for a residential solar installation.
Source: SolarTRACE, National Renewable Energy Laboratory (NREL), 2025-09-09 release. Times are medians for residential solar in the year shown. Requirements change — confirm current rules, fees and forms with the jurisdiction before you submit.